Energie « Terug naar discussie overzicht

Windpower - Far East

869 Posts, Pagina: « 1 2 3 4 5 6 7 8 9 ... 40 41 42 43 44 » | Laatste
voda
0
FFC Energy develops 50MW wind power project

FFC Energy Limited announced to have developed Pakistan’s first 50 MW wind power project at Jhimpir, District Thatta in Sindh.

Established with an investment of USD 134 million the grid interconnection facilities for this project were energized on October 30th 2012 whereby the wind farm is now connected with the national grid. This major milestone was achieved by coordinated efforts of CPPA/NTDC, HESCO and FFCEL. The project is thus ready to play a revolutionary role in strengthening Pakistan’s wind power sector.

Brig Tariq Izaz (Retd) project director said that “All 33 individual wind turbine generators and ultimately the commissioning of the whole wind farm commenced from November 7 and FFCEL expects to begin commercial operations by mid December 2012.”

The project was kicked off in 2009. Erection of all 33 wind turbine generators was successfully completed by July. By mid August, all civil, mechanical and electrical works related to the grid interconnection facility were completed. In August, the 132 KV switchyard pre commissioning was completed and was commissioned in October.

Subsequently, on November 1, a 22kV substation got commissioned. Multiple commissioning teams, foreign and local, are present at the site to complete all the remaining wind farm commissioning activities.

Source - The News.com
voda
0
Iranian firm to manufacture 3 MW wind turbines

Tehran Times reported that Iran’s MAPNA Generator Company will manufacture 2.5 MW generators through indigenizing related technology by the next 1.5 years.

Mr Hamid Amini deputy MD of MAPNA said that the wind turbines will be manufactured based on the world’s latest technology. The company plans to manufacture 9 wind turbines. Currently, Iran has the capacity to generate 10,000 MW of electricity using wind turbines.

Mr Majid Namjou energy minister of Iran said that the Islamic Republic will increase the capacity of electricity generation to over 70,000 megawatts this year.

Iran ranks the first in the Middle East in terms of electricity generation and is the 15th largest electricity producer in the world. Iran exports electricity to Azerbaijan, Armenia, Pakistan, Turkmenistan, Turkey, Iraq, and Afghanistan.

The country seeks to become a major regional exporter of electricity and has attracted more than USD 1.1 billion in investments for the construction of three new power plants.

Source - Tehran Times
voda
0
Suzlon Group bags 39.9 MW turbine orders

Business Line reported that Suzlon Group has signed contracts for supply of 39.9 MW of wind turbines with 2 public sector undertakings. The orders are valued at INR 240 crore.

The first with Gujarat State Fertilizers and Chemicals Ltd is for 29.4 MW.

GSFC has an existing installed capacity of 123.40 MW, operating in sites across Gujarat. The new order would take GSFC’s total installed capacity to 152.80 MW. The project comprises 14 units of Suzlon’s 2.1 MW wind turbines. The project is set to be commissioned in the Kutch district of Gujarat by FY13 end.

The second contract is from Bharat Electronics Ltd for 10.5 MW. BEL has an installed capacity of 3 MW, supplied by Suzlon, operating in Karnataka. The new order will take BEL’s total portfolio to 13.5 MW. The project comprises 5 units of 2.1 MW turbines. It will be commissioned in the Davangere district of Karnataka by FY13 end.

Source - Business Line
voda
0
Suzlon global installations cross 20 GW

Business Line quoted Suzlon Group said that its portfolio of projects around the world had crossed 20 GW.

The fleet, spanning generations of products and technology from 1995 includes turbines ranging from 300 KW to the largest commercially available offshore turbine of 6.15 MW.

Mr Tulsi Tanti chairman of Suzlon Group said that “From humble beginnings in 1995, we have grown into the world’s fifth largest wind turbine maker with a global fleet of over 20,500 MW operating across 32 countries. Our commitment to delivering excellence is reflected in our global uptime record between 97% and 99%, consistently above the industry average.”

Source - Business Line
voda
0
State Grid Of China carries 52% more wind power

INTERFAX-CHINA reported that State Grid Corp of China absorbed 52% more wind power in October and November than in the same period a year ago as output surged.

SGCC, the monopoly grid operator in 26 of China’s 31 administrative regions, said its network carried 16.33 terawatt hours of wind power in the period and 81.95 TWh in the first 11 months of the year. The company claimed the figure for October and November was a record.

Source – Interfax China

voda
0
Mahindras group plan wind power foray in India

Business Line reported that the USD 16 billion Mahindra group is set to enter the wind power business in India.

Though, the group is not at the moment revealing its plans.

Mr Parag Shah managing Partner at Mahindra Partners and Head of Mahindra Cleantech Ventures said that “It is in a little confidential stage. It is work in progress.”

What is clear is that the group, which has major ambitions in the cleantech space, will not get into manufacturing. That is, it is highly unlikely that there will be Mahindra wind turbine.

As Mr Shah put it, in another context, in a chat with Business Line recently, Mahindra generally speaking, would not want to be technology players. We want to be good systems integrator players as there are enough good technologies across the world and you could choose horses for courses and focus on execution.

Mr Shah said that nothing stops Mahindra EPC from becoming a large green EPC player, the idea is presumably that Mahindra would get into undertaking turnkey jobs for developing wind farms.

Source - Business Line
voda
0
Fukushima krijgt grootste windmolenpark ter wereld

Om minder afhankelijk te zijn van nucleaire energie plant Japan de bouw van het grootste windmolenpark op zee ter wereld. Het complex zal ironisch genoeg vlakbij de beruchte kerncentrale van Fukushima worden aangelegd.

Japan wil tegen 2020 in totaal 143 windturbines voor de kust van Fukushima plaatsen. De molens komen op zo'n 16 kilometer in zee te staan. Het enorme park moet een capaciteit hebben van 1 gigawatt. Daarmee wordt het groter dan de London Array, momenteel het grootste park in aanbouw.

Opvallend is dat de enorme turbines niet in de bodem geplaatst zullen worden, maar op een drijvende constructie die met ankers op zijn plaats wordt gehouden. Dat is niet alleen goedkoper, maar beschermt de turbines ook beter tegen aardbevingen en tsunami's. Als het park op volle kracht draait, zal de stroom verdeeld worden via de hoogspanningsleidingen van de vernielde kerncentrale.

Hernieuwbare energiebronnen
De plannen krijgen kritiek van vissers, die hard getroffen zijn door de kernramp. Maar de projectleiders zijn ervan overtuigd dat het windmolenpark juist een stimulans kan zijn voor de visserij in de regio, omdat het vissen zou aantrekken.

De provincie Fukushima wil tegen 2040 energie-onafhankelijk worden. Daarvoor wil het alleen gebruikmaken van hernieuwbare energiebronnen, onder meer met een grote zonnecentrale in de stad Minamisoma. Volgens CLSA Asia-Pacific, een van de grootste financiële dienstverleners in Azië, kan het land over drie jaar al een capaciteit opbouwen van 7,6 gigawatt.

Hernieuwbare energiebronnen zijn in Japan aan een sterke opmars bezig sinds de verwoestende aardbeving en tsunami in 2011 en de kernramp die daarop volgde. Japan sloot toen alle 54 kernreactoren in het land. Sindsdien zijn er nog maar enkele opnieuw opgestart, vaak met grote tegenstand van de publieke opinie.


www.ad.nl/ad/nl/1013/Buitenland/artic...
voda
0
Suzlon installed capacity crosses 150 MW in AP

Business Line reported that Suzlon Energy Ltd completion of 150 MW capacity wind power generation farms in Andhra Pradesh, with about 115 MW in the last nine months.

Following the Andhra Pradesh Government’s move to offer a tariff of INR 4.70 per unit based on the Andhra Pradesh Electricity Regulatory Commission’s nod to hike tariffs, more wind power companies are looking at the State.

Suzlon Energy in a statement said that it has crossed the installed capacity of 150 MW in Andhra Pradesh with the addition of new capacity.

Mr Rohit Modi CEO of India and Emerging Markets, Suzlon Energy, said that “Suzlon persevered to complete 150 MW of installed capacity. We credit this achievement to the support from Andhra Pradesh Government, customers and local communities.’’
Mr Kamlakar Babu CMD Of New & Renewable Energy Development Corporation of Andhra Pradesh Ltd, in a statement said that “We are optimistic about the opportunities wind energy has to offer in Andhra Pradesh. Such projects will contribute to the State’s efforts to create low carbon and green economy."

Suzlon, rated among major wind energy companies globally, has installed over 115 MW in the last nine months in the State, which accounts for nearly 60% of the total installations of 190 MW during the period. The company contributed to 233 million units to the State electricity grid in 2012.

Source – Business Line
voda
0
Suzlon bags 50 MW order

Suzlon Group the world fifth leading and India's largest wing turbine manufacture secured order for 50.4 MW wind energy project from Orange Renewable Power an emerging Independent Power Producer.

Suzlon will supply 24 units of the S88 - 2.1 MW wind turbine generators totaling 50.4 MW of capacity install operate and maintain the wind turbines for this end to end project in the Jaisalmer district of Rajasthan.

The project scheduled for completion in FY 2012 to 13.

Source - IRIS

voda
0
Mytrah gears to become largest wind power producer

Economic Times reported that Mytrah Energy Limited gears to become the largest wind based independent power producer in India by installing a capacity of 310 MW of power from wind assets. In Andhra Pradesh the company has a total capacity of 63 MW of wind assets in Vajrakarur in Anantapur district. Over INR 400 crore has been invested for the project in Vajrakarur.

A capacity of 37.4 MW in Burgula in Kurnool district is under construction and is expected to be commissioned by September 2013. MEIL has entered into a MoU with the government of Andhra Pradesh for assessing wind potential in new sites. By 2017 Mytrah aims to have an installed capacity of 1000 MW in Andhra Pradesh.

Mr Vikram Kailas MD, MEIL said that "It is a proud moment for us at Mytrah. Within just 2 years of our inception we have become the largest Independent Power Producer in Andhra Pradesh."

He added that "In the next quarter we expect to commence construction of another 100 MW in Andhra Pradesh. Also we are in advance stages of approval for a further 100 MW. Including the 100 MW which is in advance stages of approval we expect to have a cumulative of 300 MW commissioned in Andhra Pradesh by December 2014. This will involve an investment of over INR 2000 crore in the state of Andhra Pradesh which is the largest investment by an IPP in this state."

MEIL has wind farms across 6 states Andhra Pradesh, Rajasthan, Gujarat, Maharashtra, Tamil Nadu and Karnataka. The company has a total capacity of 210 MW across 8 wind farms in Kaladonger as well as Mokal, Rajasthan; Chakla, Maharashtra; Jamanwada as well as Mahidad in Gujarat. The other projects in pipeline are Vagarai in Tamil Nadu, Savalsang in Karnataka and Gotne in Maharashtra.

Source – Economic Times
voda
0
38 tonne wind farm turbine collapses in Western Japan

Gulf Times reported that a 38 tonne wind turbine crashed 50m to the ground in western Japan after the steel column supporting it snapped.

The massive Dutch made turbine, which sat atop a Japanese made steel column, was part of a wind farm in mountains near Kyoto, and it had been installed in 2001 with an expected life of at least 17 years.

A local government official said that “We are asking experts to look into the cause of the problem. We suspect metal fatigue might have played a role.”

The smashed turbine was discovered on Wednesday although it is not known when the accident occurred at the remote facility.

Wind farms have sprouted across large stretches of Japan over the last two decades as the resource-poor country seeks to capitalize on its natural bounty.

The drive for alternative energy has intensified since the Fukushima nuclear plant disaster two years ago, when a tsunami sparked reactor meltdowns.

Source - www.gulf-times.com
voda
0
Bids to open next week for building 250 MW windfarm

The Ministry of Electricity and Energy announced that it would begin accepting offers for the construction of 250 MW windfarm next week to administered as part of a Build, Operate, Own (BOO) scheme.

Mr Ahmed Imam electricity and energy minister of Egypt said that the country’s Central Bank recently released a sovereign guarantee stating that the plan would cover all necessary costs for the farm’s construction including the cost of operating for six months, expected to total USD 630 million.

Mr Imam stated that so far 10 companies have indicated they are preparing to submit offers and that seven have already conducted wind speed measurements and environmental reports on the proposed site over the last two years.

Saleh confirmed that so far six plots of land around the country had been set aside for establishing an additional 600 MW windfarm.

Source - Daily News Egypt
voda
0
Chinese wind power output in 2012 up by 41%

According to the latest statistics released by the National Energy Administration, China, the world's largest wind power producer, saw its wind power output surge 41% YoY to 100.8 terawatt hours last year.

The wind power output last year accounted for about 2% of the country's total on grid electricity.

As of the end of last year, the country's on-grid wind power capacity had increased to 62.66 gigawatt hours, 14.82 GW or 31% more than a year ago.

By the end of 2012, China had built 1,445 wind farms with 52,827 wind turbines throughout the mainland. The figure included about 1,000 state-owned wind farms, 150 privately owned wind farms.

Source - China Knowledge
voda
0
Mytrah Energy plan 100 MW wind farm in Tamil Nadu

The Hindu Business Line reported that Mytrah Energy Ltd is putting up a 100 MW farm near Coimbatore, Tamil Nadu. The farm will be fully built by September.

Mr U.B Reddy COO of Mytrah Energy told Business Line that the project is a part of Mytrah’s 240 MW expansion programme. Currently, the AIM-listed wind power company has generating capacity of 310 MW.

Mr Reddy said that “It is now building capacities in Tamil Nadu, Karnataka and Andhra Pradesh.”

The first 310 MW used only Suzlon’s wind turbines. The upcoming 240 MW is split between the Spanish wind turbine major, Gamesa and Chennai-based Regen Powertech.

He said that “The Tamil Nadu farm will use Regen Powertech’s machines.”

Source - Business Line
voda
0
TATA Power 50.4 MW wind project in Karnataka register under CDM

Tata Power, India’s largest integrated power utility today announced the successful registration of its 50.4 MW Wind power project at Gadag, Karnataka under Clean Development Mechanism program by United Nations Framework Convention on Climate Change.

The 50.4 MW wind plant at Gadag was commissioned in July 2009 and uses 63 wind turbine generators of 800 KW capacity each to harness wind energy for power generation. The Gadag plant helps in reducing an annual average of 99,100 tonne of Carbon Dioxide equivalent, by producing 107,064 MWh per year equivalent amount of clean energy.

The Gadag wind plant is Tata Power’s fourth CDM registered project, with the 50.4 MW Wind project at Khandke, Maharashtra, 50.4 MW Wind project at Samana, Gujarat 25 MW Solar project at Mithapur, Gujarat. Tata Power, as part of its sustainability initiative, is committed to reducing its carbon footprint. One of the ways towards reaching this goal is addition of clean and renewable energy generation capacity. Tata Power currently has 397 MW of operating wind power generation capacity and 28 MW of operating solar power generation capacity, making it one of the largest wind and solar power generators in India. It's subsidiary Tata Power Delhi Distribution Ltd has also commissioned a 1 MW grid connected roof top solar plant in Delhi. A 60.48 KWP solar power plant has also been functional on top of one of the building at its office in Carnac Bunder, Mumbai. The Company proposes to add 150 to 200 MW of wind and 50 MW of solar power capacity every year.

CDM is an instrument established under the Kyoto Protocol to achieve both sustainable development and contribute to the cost effective mitigation of climate change. It allows countries with emission reduction commitments to meet part of their reduction abroad, where Green House Gas abatement costs can be lower. The mechanism will also enable developing countries to attract investments in clean energy technology and assist them on a sustainable development path.

Speaking on the occasion, Mr Anil Sardana, Managing Director, Tata Power, said that “We have always established that ‘clean and renewable energy’ is the need of the hour and Tata Power will continue its efforts towards this. It gives us great pride that our fourth project, the 50.4 MW Wind plant at Gadag has been registered as under Clean Development Mechanism program by United Nations Framework Convention on Climate Change.”

Source - Strategic Research Institute

voda
0
Seajacks and Samsung Heavy to build world largest offshore wind installation vessel

Seajacks International has entered into a contract with Samsung Heavy Industries to build the world’s largest and most advanced offshore wind farm installation vessel.

The vessel has been specifically designed to meet the demands associated with working UK Round 3, Scottish territorial waters and the other North West European markets. Seajacks also has options for the construction of an additional two units.

Named Seajacks Scylla, the new vessel is based on the Gusto MSC NG14000X design and will be the 5th new self propelled jack up to join the Seajacks fleet since 2009. The vessel will be equipped with a 1500 tonne leg encircling crane, incorporate useable deck space in excess of 5000m2, and have over 8000t of available variable load.

Sailing at speeds of 12 knots or over, Scylla will be outfitted with 105 meter long legs that have the ability to install components in water depths of up to 65 meter. Seajacks is a leading offshore installation contractor that services both the offshore wind and oil and gas industries.

Based in the UK, the company recently expanded from its core market in the North Sea and North West Europe by establishing ‘Seajacks Japan’ as a platform from which to service the Asian market.

Recently, Seajacks completed the successful installation of all 80 monopiles at the Meerwind Offshore Wind Park on schedule, despite having experienced significantly worst weather than anticipated this winter.

As part of its role as Main Installation Contractor at the German site, Seajacks is responsible for the installation of all turbines and foundations, as well as the scour installation, grouting and noise mitigation for the project.

Mr Blair Ainslie CEO of the Seajacks Group said that “Seajacks Scylla is a significant milestone for Seajacks and for the offshore wind industry. She is a Round 3 vessel and is more technically advanced than any other installation vessel that we see on the market today.”

Source - Strategic Research Institute
voda
0
Japan Prepares to Float Offshore Wind Industry

10/01/2013 | Sonal Patel

A prototype 100-kW floating wind turbine that has been tested off Nagasaki near Japan’s Kabashima Island since May 2012 is slated to be replaced by a full-scale, grid-connected 2-MW wind turbine this fall. The demonstration backed by Japan’s Ministry of Environment, Kyoto University, Fuji Heavy Industries, Toda Construction, and the National Maritime Research Institute of Japan features a floating spar buoy wind turbine built by Japan Steel Works and Hitachi. Following initial operation and data collection, the project will be upgraded to a Fuji Heavy Industries 2-MW wind turbine. The project will mark a major point of progress for the world’s infant deep water offshore wind industry.

According to a new report from the European Wind Energy Association, at the end of 2012, 1,662 turbines totaling 5 GW of installed offshore wind capacity were spread across 55 wind farms in 10 European countries. But, with the exception of two turbines, Europe’s grid-connected offshore wind turbines rely on fixed foundations, and the vast majority of those are on monopile foundations, the organization notes. Gravity-based substructures are the second-most-common foundation type, followed by space frame structures. Only Statoil’s 2.3-MW Hywind project—the world’s first large-scale floating wind structure installed in 2009 in Norway—and the 2-MW Windfloat, installed off the Portuguese coast in 2011 by Principle Power and EDP, are installed on floating substructures.

At least six experimental floating structures are in a test phase globally: SeaTwirl, SWAY, Blue H, and Poseidon in Europe; the WindLens in Japan; and the DeepCwind floating turbine in the U.S. Another 35 designs for water depths of more than 50 meters are under development worldwide. The majority (60%) are located in Europe, 10% are in the U.S., and 23% are in Japan.

Experts say deep water offshore wind potential in the U.S. is immense, owing to long coastlines and a good wind resource, but there are no offshore wind farms operating to date. In May 2013, the University of Maine and the DeepCwind consortium—comprising 30 companies—put online the first 20-kW prototype (Figure 3). Also, the Department of Energy has announced $168 million in funding over the next six years for seven offshore wind demonstration projects—including three floating projects.

In Japan, which has the world’s sixth-largest Exclusive Economic Zone and a long maritime heritage, more than 80% of offshore wind energy resources are located in deep waters. The country’s government has been funding research on deep offshore structures for more than two decades, but interest has kicked up since the March 2011 Fukushima nuclear accident as the government focuses on putting online more renewables. An estimated 5 GW to 6 GW have been envisioned for the country by 2030.

Including the prototype WindLens project in Hakata Bay—which features two wind turbines of just 3 kW each—at least three national offshore wind projects have been announced, one of which could use a floating substructure. That project is supported by Japan’s Ministry of Economy, Trade and Industry and involves a $250 million demonstration off the coast of Fukushima. Plans call for the installation of several floating offshore turbines, including three types of floating substructures with two different turbine sizes: 2 MW in phase 1 and 7 MW in phase 2. The Fukushima offshore project is being developed by an industry consortium led by Marubeni Corp. and includes Mitsubishi and Hitachi. Mitsubishi has, meanwhile, announced plans for the development of a new 7-MW turbine with a hydraulic drive, designed to operate on semi-submersible floating platforms in deep water off the coast of Fukushima. Among the consortium’s ambitious goals are to reach 1 GW of floating capacity.
voda
0
Macarthur Wind Farm, Victoria, Australia

12/01/2013 | Sonal Patel

Owner/operator: AGL Energy/Malakoff Corporation Berhad

Fully commissioned in January 2013, the 420-MW Macarthur Wind Farm is the largest wind farm in the Southern Hemisphere. But sourcing and erecting 140 wind turbines for this massive project was logistically challenging and required a rethink on several levels.

Though endowed with some of the world’s largest coal resources, Australia—whose southern coasts experience strong westerly winds called the “Roaring Forties”—also has wind power as a natural choice. For centuries, these powerful, largely unhampered west-to-east air currents, which are caused by a combination of air being displaced from the Equator towards the South Pole and the Earth’s rotation, helped speed ships sailing from Europe to Australasia. Today, they furnish hundreds of sites in South Australia with wind speeds averaging 8 or even 9 meters per second (m/s) at 50 meters (m) above the ground—giving the nation wind power resources that excel by world standards.

Yet the country’s wind power sector is just getting started. At the end of 2012, wind turbines with a total nameplate capacity of 2,548 MW supplied more than 7,700 GWh, or 3.4%, of Australia’s overall electricity demand. Wind’s outlook is healthy: The current renewable energy target (RET) set by the Australian government requires 20%—or more than 45,000 GWh—of the country’s total power generated to be sourced from renewables by 2020, and at least 19 GW of new wind projects are in the pipeline.

Industry analysts forecast the growth of wind power will be sustained despite the conservative Liberal Party’s sweep to power in the Sept. 7 election, which ended a six-year term led by the largely wind-supportive Labor government. Newly elected Prime Minister Tony Abbott has pledged to repeal the year-old national carbon tax of A$23 per metric ton of carbon dioxide equivalent emissions that was expected to last until July 2015, after which the country was to transition to an emissions trading scheme. But he has also pledged to shutter the publicly funded A$10 billion Clean Energy Finance Corp. (CEFC), and press on with a biennial review of the RET policy, begun in January 2010 and next due for review in 2014.

Thinking Big

In this context, full completion last January of the 420-MW Macarthur Wind Farm in the southeastern state of Victoria, Australia’s most noteworthy wind installation to date, marked a tremendous milestone for the country’s fledgling sector.

More than 350 people were directly employed during the 30-month construction of this A$1 billion project’s 140 wind turbines near Hamilton, about 245 kilometers (km) west of Melbourne—making it the largest investment in Australian renewable energy since the 1974-completed Snowy Mountains Scheme, a hydroelectric project widely considered an engineering wonder.

Development of the Macarthur Wind Farm was initiated in 2007 by AGL Energy Ltd. (AGL) and its former 50:50 joint venture partner Meridian Energy, which is based in New Zealand. The project is now owned by AGL and Malakoff Corporation Berhad. Though primarily built by a consortium comprising Australian infrastructure and mining firm Leighton Contractors and Danish wind turbine maker Vestas, a number of local suppliers also participated. Keppel Prince Engineering, from Portland, Victoria, for example, manufactured 80 of the 140 wind towers. The remaining 60 towers were supplied by Adelaide-based RPG Australia.
Bijlage:
voda
0
Long term demand outlook for wind power in India remains strong - ICRA

PTI reported that credit rating agency ICRA said that the long term demand outlook for wind power remains strong mainly on account of cost competitiveness, regulatory support and the generation-based incentive benefit.

ICRA said in a study that "The long term demand outlook for the wind energy sector remains strong, aided by the cost-competitiveness of wind energy against the fossil fuels and regulatory support in place byway of renewable purchase obligation norms for the obligated entities, besides the financial support by way of GBI benefit."

The study said that the sector is facing challenges on the RPO front as over 60% of 28 states are yet to meet the long-term trajectory for RPO norms.

RPOs are the minimum stipulated percentages of the total power that electricity distribution companies and some large power consumers need to purchase from renewable energy sources.

The survey said that the long term trajectory for RPO is in place only in 11 out the 28 states.

State electricity regulatory commissions in 20 states have stipulated the RPO norms for FY 2015, while of the remaining eight states, Meghalaya and Uttar Pradesh have put in provisions for continuation of the prevailing RPO for subsequent years until new norms are approved by the state regulators.

According to the survey, discoms in Himachal, Karnataka and Tamil Nadu have completely met the RPO norms as specified for FY 2013, while those in Gujarat, Maharashtra and Rajasthan, the compliance is in the range of 90% to 95% of the targeted RPO for the year.

Though the national action plan for climate change has specified minimum RPO target of 5% in FY 2010, to be increased by 1% every year over 10 years to reach 15% by FY20, majority states continue to remain lower than the RPO trajectory.

Source - PTI
voda
0
Veer Energy & Infrastructure to set up 12 MW wind power project at Vinjalpur

eer Energy & Infrastructure said that its board of directors has decided to set up 12MW wind power project situated at Vinjalpur - Gujarat through its proposed subsidiary Shruti Power Projects.

The board has also decided to give corporate guarantee of INR 525.6 million to Indian Renewable Energy Development Agency for its term loan sanctioned to its proposed subsidiary Shruti Power Projects.

Source – Strategic Research Institute
869 Posts, Pagina: « 1 2 3 4 5 6 7 8 9 ... 40 41 42 43 44 » | Laatste
Aantal posts per pagina:  20 50 100 | Omhoog ↑

Meedoen aan de discussie?

Word nu gratis lid of log in met uw e-mailadres en wachtwoord.

Direct naar Forum

Markt vandaag

 AEX
865,36  0,00  0,00%  18 apr
 Germany40^ 17.751,90 -0,48%
 BEL 20 3.826,58 0,00%
 Europe50^ 4.919,39 -0,35%
 US30^ 38.013,46 0,00%
 Nasd100^ 17.548,80 0,00%
 US500^ 5.049,25 0,00%
 Japan225^ 38.001,71 0,00%
 Gold spot 2.383,29 +0,16%
 EUR/USD 1,0635 -0,08%
 WTI 82,08 0,00%
#/^ Index indications calculated real time, zie disclaimer

Stijgers

AALBERTS NV 0,00%
ABN AMRO BANK... 0,00%
Accsys 0,00%
ACOMO 0,00%
ADYEN NV 0,00%

Dalers

AALBERTS NV 0,00%
ABN AMRO BANK... 0,00%
Accsys 0,00%
ACOMO 0,00%
ADYEN NV 0,00%