TraderRon
0
quote:

Dongen schreef op 22 november 2016 09:20:

[...]???????????????????????

It says: "The results of the investigations confirm to us that the contractual requirements and the design intent have not been realised."

The report also recommends that BAM Nuttall pay for £36.5 million of repair work as well as cover legal costs.

Since October 2013 the Council has spent £3.07 million on legal fees and paid £192,000 for the recent investigations.

Councillors are now being asked to support a twin track approach of trying to negotiate with BAM Nutall while also starting legal proceedings.


Dat is 40 miljoen pond waar ze gok ik niet onderuit gaan komen helaas.
manuss
0
quote:

TraderRon schreef op 22 november 2016 09:33:

[...]

It says: "The results of the investigations confirm to us that the contractual requirements and the design intent have not been realised."

The report also recommends that BAM Nuttall pay for £36.5 million of repair work as well as cover legal costs.

Since October 2013 the Council has spent £3.07 million on legal fees and paid £192,000 for the recent investigations.

Councillors are now being asked to support a twin track approach of trying to negotiate with BAM Nutall while also starting legal proceedings.


Dat is 40 miljoen pond waar ze gok ik niet onderuit gaan komen helaas.
Ouwe troep die steeds opgerakeld wordt, leuk voor de shorters. Gelieve hier niet meer op in te gaan op dit forum zolang er geen echt nieuws is/komt. Wat hebben we hieraan!!??!!
TraderRon
0
quote:

manuss schreef op 22 november 2016 09:38:

[...] Ouwe troep die steeds opgerakeld wordt, leuk voor de shorters. Gelieve hier niet meer op in te gaan op dit forum zolang er geen echt nieuws is/komt. Wat hebben we hieraan!!??!!
Normaal gesproken heb je gelijk.
Maar als een onafhankelijk bureau een onderzoek gedaan heeft dat ook nog met goedkeuring van BAM is gedaan en aangeeft dat BAM dit moet gaan dokken.
Dan is die kans vrij groot zeg maar.
Of ik dat nu wel of niet wil.

BAM Nuttall denied there were any further defects and the Council accepted their proposal to carry out a joint investigation into the condition of the Busway.

The subsequent report from Capita concluded that the defects do represent a breach of contract by BAM Nutall and found additional defects that need to be repaired.
[verwijderd]
0
Snel instappen, Ron. Veel lager krijg je ze niet. Zonder BAMmen zitten voelt meer ellendig dan mét BAMmen meedeinen op de emotie-golven. Want als die koers-tsunami er aan komt, ben je te laat ;-)
[verwijderd]
0
Goed gezegd TraderRon, de kop niet in het zand steken. Daar kom je het verste mee.
manuss
0
quote:

€d_Modus Vivendi schreef op 22 november 2016 09:46:

Heijmans neemt Bam over naar hun koers te oordelen ;)
Voor de koers van heden 4,77 en een beetje ga ik er over nadenken.
€d_Modus Vivendi
0
quote:

TraderRon schreef op 22 november 2016 09:33:

[...]

It says: "The results of the investigations confirm to us that the contractual requirements and the design intent have not been realised."

The report also recommends that BAM Nuttall pay for £36.5 million of repair work as well as cover legal costs.

Since October 2013 the Council has spent £3.07 million on legal fees and paid £192,000 for the recent investigations.

Councillors are now being asked to support a twin track approach of trying to negotiate with BAM Nutall while also starting legal proceedings.


Dat is 40 miljoen pond waar ze gok ik niet onderuit gaan komen helaas.
Die 40 miljoen euro hangt wel weer boven de markt. Helaas gaat dit zwaar ten koste van de winst. In vergelijking met die paar centen die Heijmans voor de Frisiaweg gaat lijden staan hiermee in schril contrast. Heijmans kan er nog onder uit komen, maar BAM zal die 40 miljoen toch een keer moeten ophoesten. Als ze het weer tot een proces laten komen kost het alleen maar nog meer. Hoeveel projecten moet Bam wel niet aannemen om die 40 miljoen terug te verdienen?
Kortom het is weer een ramp die al jaaaaaren voort duurt.
Vooralsnog zwijgt Bam weer in alle talen. Dat deden ze eerder ook al. Hebben nooit iets van ze gehoord toen het onderzoek ging plaatsvinden eind 2015. Dat zou een half jaar duren. Bam ontkende destijds en zei dat het allemaal media verhalen waren. Je kunt dit het huidige bestuur wel degelijk aanrekenen. Zij zijn niet open geweest en wisten dat dit lijk uit de kast ging komen vroeg of laat.
€d_Modus Vivendi
0

Hunts Post



Independent report into guided busway defects says contractor BAM Nuttall is responsible

09:00 22 November 2016

Daniel Mansfield

An independent report carried out into defects on the guided busway has supported Cambridgeshire County Council’s claim that the contractor, BAM Nuttall, is responsible and should pay for repairs.

The guided buswayThe guided busway

Members of the county council’s general purposes committee will meet on November 29 to look at the independent engineer’s report into the findings of investigations carried out jointly for the authority and BAM Nuttall.

The report, carried out by Capita, concludes that the defects represent a breach of contract by the contractor who designed and built the busway, and noted that additional defects could also require repair.

The paper to be put before councillors recommends that the defects should be rectified with initial costs for the work at £36.5 million and this, as well as legal costs, should be picked up by BAM Nuttall.

Councillors on the committee are being asked to agree that the defects are rectified as part of one programme rather than on a piecemeal basis as they deteriorate, which, it is estimated, would cost considerably more in the long run and cause more disruption to services.

Councillors are being asked to support a dual approach of seeking, if possible, to negotiate with BAM Nuttall while also starting legal proceedings.

The council believes the works could be carried out in sections to allow other parts of the busway to remain open while the defects are rectified.

According to the engineer’s report, the principal defects include:

• Vertical and horizontal steps have developed at the joints between the precast track sections or ‘ladders’

• The foundations of the guideway are moving differentially; and

• The concrete of the guideway is spalling (slivers of concrete breaking off corners) in numerous locations

Adrian Savory, operations director for BAM Nuttall, said: “I am really surprised that the council hasn’t come to talk to us before publishing this latest report.

“BAM Nuttall is totally committed to ensuring that the busway performs as it should. If there is anything wrong with the busway for which BAM Nuttall is responsible, BAM Nuttall will put it right.

“We’ve told the council this many times and invited them to come to us to explain the basis for their concerns. BAM Nuttall would welcome the opportunity to discuss the latest report with the council.”

The report comes following a lengthy legal dispute between the county council and BAM Nuttall which ended in 2013 with the latter agreeing to pay back £33million of the £147.7million project costs.

The parties had argued over who would be responsible for an overspend for the busway route between St Ives and Cambridge.

The initial contract was for 130 weeks of work, with the completion date on February 27, 2009, but the busway construction was not completed until April, 2011, and not open for use until August of that year as the county council raised concerns about defects.
M M
0
quote:

€d_Modus Vivendi schreef op 22 november 2016 10:27:

Hunts Post



Independent report into guided busway defects says contractor BAM Nuttall is responsible

09:00 22 November 2016

Daniel Mansfield

An independent report carried out into defects on the guided busway has supported Cambridgeshire County Council’s claim that the contractor, BAM Nuttall, is responsible and should pay for repairs.

The guided buswayThe guided busway

Members of the county council’s general purposes committee will meet on November 29 to look at the independent engineer’s report into the findings of investigations carried out jointly for the authority and BAM Nuttall.

The report, carried out by Capita, concludes that the defects represent a breach of contract by the contractor who designed and built the busway, and noted that additional defects could also require repair.

The paper to be put before councillors recommends that the defects should be rectified with initial costs for the work at £36.5 million and this, as well as legal costs, should be picked up by BAM Nuttall.

Councillors on the committee are being asked to agree that the defects are rectified as part of one programme rather than on a piecemeal basis as they deteriorate, which, it is estimated, would cost considerably more in the long run and cause more disruption to services.

Councillors are being asked to support a dual approach of seeking, if possible, to negotiate with BAM Nuttall while also starting legal proceedings.

The council believes the works could be carried out in sections to allow other parts of the busway to remain open while the defects are rectified.

According to the engineer’s report, the principal defects include:

• Vertical and horizontal steps have developed at the joints between the precast track sections or ‘ladders’

• The foundations of the guideway are moving differentially; and

• The concrete of the guideway is spalling (slivers of concrete breaking off corners) in numerous locations

Adrian Savory, operations director for BAM Nuttall, said: “I am really surprised that the council hasn’t come to talk to us before publishing this latest report.

“BAM Nuttall is totally committed to ensuring that the busway performs as it should. If there is anything wrong with the busway for which BAM Nuttall is responsible, BAM Nuttall will put it right.

“We’ve told the council this many times and invited them to come to us to explain the basis for their concerns. BAM Nuttall would welcome the opportunity to discuss the latest report with the council.”

The report comes following a lengthy legal dispute between the county council and BAM Nuttall which ended in 2013 with the latter agreeing to pay back £33million of the £147.7million project costs.

The parties had argued over who would be responsible for an overspend for the busway route between St Ives and Cambridge.

The initial contract was for 130 weeks of work, with the completion date on February 27, 2009, but the busway construction was not completed until April, 2011, and not open for use until August of that year as the county council raised concerns about defects.
Hoi Ed,

Klinkt mij meer als een langlopende garantie (zonder reparatiekosten), dan als een te betalen afkoop van een claim.
BAM zegt in feite, er is al een keer gesetteld voor een groot bedrag en percentage, dan is het lastig nog eens via de rechter te settelen (zou dan meer dan de helft niet betaald zijn door opdrachtgever), maar dat is ook niet nodig, want wij nemen onze verantwoordelijkheid. Als de baan niet meer gebruikt kan worden (of dit dreigt) dan zorgen wij voor een oplossing gedurende de economische levensduur. Dus dan is een rechtszaak of reparatie voordat het probleem zich voordoet, ook helemaal niet nodig. Zo smeer je kosten over vele jaren en trek je er lering uit hoe je dit volgende keer beter moet opschrijven en laat je de klant niet in de steek.

€d_Modus Vivendi
0
An independent report carried out into defects on the guided busway has supported Cambridgeshire County Council’s claim that the contractor, BAM Nuttall, is responsible and should pay for repairs.

Dit was 2014:
The troubled project - the largest of its type in the UK - was originally due to be finished in early 2009 for a total cost of £116m, but was eventually completed in April 2011 at a reported cost of £152m.

Last year Bam Nuttall paid out £33m in an out of court settlement over a dispute over cost overruns on the project following the delay.

But last week fresh expert advice given to the council by a lawyer and consultant Capita said there are further defects on the project, amounting to £31m of work, that should be fixed by the contractor.


Dat settelen van destijds had te maken met de veel te late oplevering.
Het gaat nu om reparaties twv 40 miljoen dat een onpartijdig bureau, waarmee Bam akkoord ging, heeft becijferd en beoordeeld. Bam kan bij niet uitvoeren een proces verwachten. En reken maar dat de rechter er zin in heeft en de council helemaal, want het is allemaal belastinggeld..
M M
0
quote:

€d_Modus Vivendi schreef op 22 november 2016 11:25:

An independent report carried out into defects on the guided busway has supported Cambridgeshire County Council’s claim that the contractor, BAM Nuttall, is responsible and should pay for repairs.

Dit was 2014:
The troubled project - the largest of its type in the UK - was originally due to be finished in early 2009 for a total cost of £116m, but was eventually completed in April 2011 at a reported cost of £152m.

Last year Bam Nuttall paid out £33m in an out of court settlement over a dispute over cost overruns on the project following the delay.

But last week fresh expert advice given to the council by a lawyer and consultant Capita said there are further defects on the project, amounting to £31m of work, that should be fixed by the contractor.


Dat settelen van destijds had te maken met de veel te late oplevering.
Het gaat nu om reparaties twv 40 miljoen dat een onpartijdig bureau, waarmee Bam akkoord ging, heeft becijferd en beoordeeld. Bam kan bij niet uitvoeren een proces verwachten. En reken maar dat de rechter er zin in heeft en de council helemaal, want het is allemaal belastinggeld..
Betekent dan dat totaal 80 mio door BAM betaald wordt van een totaal project van 140 mio. Dat gaat niet gebeuren Ed, juridisch heb ik nog nooit gezien dat iets geleverd wordt dat gebruikt wordt als zodanig en dat meer dan de helft niet betaald hoeft te worden Ed. Maar goed hoor we verschillen van inzicht geen punt.
[verwijderd]
0

leuke puzzel :-)

oorspronkelijk prijs begin 2009 worden afgerond voor een totaalbedrag van £ 116 m,
maar werd uiteindelijk afgerond in april 2011 op een gerapporteerde prijs van £ 152 m.

Vorig jaar Bam Nuttall uitbetaald, £ 33 m in een minnelijke schikking over een geschil over kostenoverschrijdingen aan het project na de vertraging

Dus zoals ik het begrijp £ 152 m - £ 33 m = £ 119 m is er dus uitbetaald aan BAM.

Maar vorige week verse deskundig advies gegeven aan de gemeente door een advocaat en adviseur Capita zei dat er nog gebreken aan het project, voor een bedrag van £ 31 m van het werk, dat moet worden vastgesteld door de aannemer.

Dus er was £ 119 m uitbetaald en als ze in het ongelijk zouden worden gesteld er nog £ 31 m moeten worden betaald.

Totale klus opgeleverd dan: £ 119 m - £ 31 m = £ 88 m

wie o wie

A3aan
0
Zit te overwegen weer in BAM te stappen. In het verleden flinke verliezen geleden met BAM. Daarna toch weer eens ingestapt, omdat ik dacht dat het ergste achter de rug was, maar toen ook weer flink verloren. Nu rondom 4,00 lijkt mij aandeel weer koopwaardig, maar als ik dan huidige berichten lees krijg ik toch weer het gevoel: "Nee, niet weer, al die miscalculaties en fouten. Houdt het dan nooit op"? Ik twijfel nu toch echt.
M M
0
quote:

A3aantje schreef op 22 november 2016 12:25:

Zit te overwegen weer in BAM te stappen. In het verleden flinke verliezen geleden met BAM. Daarna toch weer eens ingestapt, omdat ik dacht dat het ergste achter de rug was, maar toen ook weer flink verloren. Nu rondom 4,00 lijkt mij aandeel weer koopwaardig, maar als ik dan huidige berichten lees krijg ik toch weer het gevoel: "Nee, niet weer, al die miscalculaties en fouten. Houdt het dan nooit op"? Ik twijfel nu toch echt.
Niet doen dan. Afwachten hoe het loopt zou ik zeggen
[verwijderd]
0
quote:

A3aantje schreef op 22 november 2016 12:25:

Zit te overwegen weer in BAM te stappen. In het verleden flinke verliezen geleden met BAM. Daarna toch weer eens ingestapt, omdat ik dacht dat het ergste achter de rug was, maar toen ook weer flink verloren. Nu rondom 4,00 lijkt mij aandeel weer koopwaardig, maar als ik dan huidige berichten lees krijg ik toch weer het gevoel: "Nee, niet weer, al die miscalculaties en fouten. Houdt het dan nooit op"? Ik twijfel nu toch echt.
Doe het NIET!! Echt niet doen. Niet opnieuw verliezen...
En mocht je de verleiding niet kunnen weerstaan, meld het dan even van tevoren. Dan ga ìk er uit ;-)
[verwijderd]
0
quote:

Crusader schreef op 22 november 2016 12:38:

[...]

Doe het NIET!! Echt niet doen. Niet opnieuw verliezen...
En mocht je de verleiding niet kunnen weerstaan, meld het dan even van tevoren. Dan ga ìk er uit ;-)
Ik denk dat het allemaal wel losloopt met BAM, ze zitten in ieder geval op de goede weg, en er zijn goede maatregelen getroffen die het bedrijf toekomstbestendiger moeten maken. Bij de jaarcijfers 2016, ergens volgend jaar in februari geloof ik, zal niet alleen naar het absoulte resultaat worden gekeken, maar juist naar de ontwikkeling t.o.v. vorige jaren. Dat zal dan behoorlijk positief zijn, althans daar ga ik vanuit.
[verwijderd]
0
€d_Modus Vivendi
0
quote:

RusNetCom schreef op 22 november 2016 12:11:

leuke puzzel :-)

oorspronkelijk prijs begin 2009 worden afgerond voor een totaalbedrag van £ 116 m,
maar werd uiteindelijk afgerond in april 2011 op een gerapporteerde prijs van £ 152 m.

Vorig jaar Bam Nuttall uitbetaald, £ 33 m in een minnelijke schikking over een geschil over kostenoverschrijdingen aan het project na de vertraging

Dus zoals ik het begrijp £ 152 m - £ 33 m = £ 119 m is er dus uitbetaald aan BAM.

Maar vorige week verse deskundig advies gegeven aan de gemeente door een advocaat en adviseur Capita zei dat er nog gebreken aan het project, voor een bedrag van £ 31 m van het werk, dat moet worden vastgesteld door de aannemer.

Dus er was £ 119 m uitbetaald en als ze in het ongelijk zouden worden gesteld er nog £ 31 m moeten worden betaald.

Totale klus opgeleverd dan: £ 119 m - £ 31 m = £ 88 m

wie o wie

Niet betaald AAN maar DOOR Bam.

The report also recommends that BAM Nuttall pay for £36.5

million of repair work as well as cover legal costs.

Since October 2013 the Council has spent £3.07 million on legal fees and paid £192,000 for the recent investigations.

en 31 miljoen £ door Bam betaald wegens overschrijding levertijd in 2013.
1.508 Posts, Pagina: « 1 2 3 4 5 6 ... 58 59 60 61 62 63 64 65 66 67 68 ... 72 73 74 75 76 » | Laatste
Aantal posts per pagina:  20 50 100 | Omhoog ↑

Meedoen aan de discussie?

Word nu gratis lid of log in met uw e-mailadres en wachtwoord.

Direct naar Forum

Detail

Vertraagd 7 jun 2024 17:35
Koers 3,960
Verschil -0,040 (-1,00%)
Hoog 4,000
Laag 3,930
Volume 886.401
Volume gemiddeld 1.217.870
Volume gisteren 1.393.874